How to schedule a report with weekly delivery for Last seven Days

Environment

Adobe Analytics

Schedule Reports

Steps

1:-Pull report.
2:-Select the date as last seven days from the day reports is getting created.
For Eg:-Report is getting created on Wednesday then select the date range as Last Wednesday until Yesterday(Tuesday).
3:-Run the report
4:-Click on scheduling the report{Every tool scheduling option is different}.
    ->https://marketing.adobe.com/resources/help/en_US/dsc/t_schedule_delivery.html
5:-Click on Advance Delivery Option.
    ->https://marketing.adobe.com/resources/help/en_US/dsc/r_advanced_format_settings_dsc.html
6:-Select Scheduling option and then Schedule for Later
7:-Select Start and End as Rolling Daily
8:-Delivery Frequency as Weekly
9:- In starting on option:-Select the date from which you want schedule should deliver.
     ->For eg:-If the schedule is to deliver on Monday, select Monday's Date.
10:-Click schedule.
The schedule delivers on Monday with the data as Last Monday to Sunday.

Additional resources

This work is licensed under a Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported License  Twitter™ and Facebook posts are not covered under the terms of Creative Commons.

Legal Notices   |   Online Privacy Policy